How do you get financing for a home that is yet to exist?
Some assume that you buy your land first and then acquire some sort
of bridge loan or improvement financing. While this is an approach you
could take, you will find that there are very big consequences to selecting
the wrong type of construction financing. At a minimum, the wrong financing
package can cost you several thousand dollars in extra closing costs,
and closing costs have to be paid in cash. We have prepared the following
information to help you sort through the quagmire of construction financing.
Since the objective is to have a permanent loan on your
completed home, regardless of the type of financing, lenders will insist
that you must first be able to qualify for the permanent loan. Provided
that there are no issues on that point, lenders may offer construction-only
financing, "permanent" (regular first mortgage) financing,
or various combinations of both. Your Emerge Homes representative will
generally recommend a construction-to-permanent financing
package. This approach features only one settlement, one set of closing
costs. The transition is painless. The only noteworthy drawback is that,
while construction-to-permanent loans are rapidly catching
on among mortgage lenders, there are fewer lenders competing for your
loan.
Short-term construction-only loans are not generally
your best option. They're fine for builders who will be selling
the house after it's constructed, but they're a bit risky for you because
you will then have to seek your permanent mortgage elsewhere.
Construction-only loans are
also more expensive in the long run because you will have to pay
extra closing costs. These loans must be paid off in full when construction
is complete, and usually within 12 months or so even if construction
is not complete.
If you're building a home which you intend to occupy,
most lenders will offer you combination "construction permanent"
financing. Customs vary from place to place, but there are two basic
versions:
The first is a short-term construction-only loan which
automatically "rolls" into the permanent mortgage when construction
is complete. It's important that these two separate loans be treated
as a package. If not, you will have to pay additional closing costs,
and possibly, re-qualify for the permanent loan.
The second type is a single long-term permanent mortgage
in which the money is paid out as the construction proceeds. Single
loan financing is generally the lowest cost, most desirable financing,
but you may or may not be able to arrange it. Policies vary, so check
additional lenders if the first one doesn't offer this type of financing.
Construction loans, whether construction-only or part
of a construction- permanent package, are usually interest-only. That
is, you make no payments to principal until construction is complete.
The interest rate is typically about 1% to 3% above the lender's Prime
Rate at the time the loan is made. Keep in mind, though, that the higher
rates will not apply to the permanent portion of the package.
Special Risks In Construction Financing
Your financing 'package' will most likely be comprised of separate construction
and permanent loans. This type of financing poses several risks, primarily
due to events which can occur during the period between the time you
are initially qualified for financing, and when you must be re-qualified
before the permanent loan can be closed.
Anything which affects your ability to re-qualify could
result in losing your new home, and most or all of your down payment
or the money you've invested in a lot.
If construction costs are higher than expected, you
may have to come up with extra cash to keep the Loan-To-Value (or the
Loan-to-Cost) ratio to the allowable maximum. Be sure you ask about
the lender's policy in this event -- just when you will have to come
up with the money, for example.
With Emerge Homes you will generally be able to avoid
this type of problem because we generally provide you a fixed-price
contract. Also, you may be able to realize a lower overall cost with
a cost-plus contract if no unforeseen problems arise, so consider your
risks carefully.
It may seem obvious, but don't ever make changes or
add any 'extras' without prior written cost estimates. Be sure you understand
your lender's policy regarding changes. Prior approval is almost always
mandatory, so be sure to notify your lender before you authorize even
small changes -- and be sure the approval is in writing.
One the greatest risks you can face is that of rising
interest rates. The interest rate on your permanent loan will be set
at, or shortly before, closing. If rates have risen during the 6 months
or so during construction, you may no longer be able qualify at the
higher rate. About the only thing you can do in this situation is come
up with enough extra cash to bring the loan amount down low enough for
you to be able to meet the all-important qualification requirements,
which we discuss shortly.
Talk to the lenders that you're considering. Try to
determine how each would react if a problem arises. It's unlikely that
you'll get any definitive answers -- lenders generally prefer a case-by-case
approach -- but you may be able to get an indication of how much latitude
you may receive. A lender might be willing, for example, to extend the
construction loan for an extra month or two to allow time for you to
raise the extra money.
Finally, if at all possible -- even if you have to cut
back on your plans a bit -- maintain an extra "cushion" of
about 5% - 10% of the total amount you expect to spend. The best way
to do this is to postpone something, perhaps a garage, fancy flooring,
or other part of your project that can be easily added later - it's
just good insurance.
When Construction Begins
After the loan closing, the builder can begin construction. This is
typically done in various stages which follow a logical progression:
the land is cleared, the foundation is excavated and poured, the framework
is built, etc. In many cases, the builder does not do the work himself;
rather, he employs numerous independent businesses as "subcontractors"
for jobs like plumbing, masonry, wiring, framing, etc. The builder's
job, in this case, is rather like the conductor of a symphony: he coordinates
the many separate parts to create a finished whole.
It's also the builder's responsibility to supply the
materials; the lender will reimburse him at several prearranged stages
of the construction. These "disbursements" -- which, in fact,
will be released to your attorney as the trustee -- will not be granted,
however, until the lender performs inspections on the completed work
and is satisfied as to its completion. Here's a typical advance schedule.
You'll see that, even though there are only a few advances, there are
well over a dozen phases to the construction itself.
A good lender is a protection to you. They dont
pay us until a phase of work is complete. You and the lender will approve
a draw schedule with a series (usually 4 or 5) of progression payments,
usually based on percentages of the full loan amount. Here is a common
draw formula:
First Advance (Generally 15% of Construction Costs)
Second Advance (Generally 40% of Construction Costs)
Third Advance (Generally 20% of Construction Costs)
Final advance (Generally 25% of Construction Costs)
There are many choices for your construction financing
needs.